Piling Complete in Record Time

We at Westone are very pleased to be able to report that our contractor, Casais together with their subcontractor, Bullivant, have now completed the piling operations. The contract programme gave 10 May 2016 for completion so we are ahead of schedule by about 2.5 weeks!  Congratulations to the team for such impressive progress - and stay [...]

By | 2016-12-09T10:01:53+00:00 April 21st, 2016|Uncategorized|Comments Off on Piling Complete in Record Time

Piling Is Almost Complete – W1 Soon to Rise out the Ground!

Since our last update our contractors have made great progress - 300 out of 340 piles are now in place and the pile caps and associated foundations are advancing according to programme. The tie in to the fresh and salt water supply is complete and approved by the utility provider, and the design definition is almost [...]

By | 2016-12-09T10:01:53+00:00 April 12th, 2016|Uncategorized|Comments Off on Piling Is Almost Complete – W1 Soon to Rise out the Ground!